Picture show inside of First floor Brick work
3000 sft two storeyed house for Mr.Jairaj Iyer and Ms.Usha Iyer at Mambra near Koratty,Kerala state
Saturday, June 26, 2010
Tuesday, June 22, 2010
Brick work continuing
Brick work for first floor continued with ground floor Electrical work in progress.Pictures show precast stair steps being fixed for going up to roof top and brick work in progress
Friday, June 18, 2010
Brick work progressing
Pictures below show brick work for first floor progressing.Precast stair for Roof top are being concreted and kept in place as brick work progresses
Friday, June 11, 2010
Brick work reaching First Floor lintel level
Brick work for first floor,electrical cutting for Ground Floor,Manufacturing of door and windows for first floor are in progress.Pictures show work in progress.